Global Law Experts Logo
energy lawyers france

Energy Lawyers France 2026: Decree No.21, PPE Targets and Project Compliance

By Global Law Experts
– posted 3 hours ago

France’s energy regulatory landscape shifted decisively on 20 February 2026 with the publication of Law Decree No.21, introducing mandatory operational obligations for renewable generators, recalibrating the Programmation pluriannuelle de l’énergie (PPE) targets, and expanding energy audit requirements across the sector. For energy lawyers France-wide, and for every developer, independent power producer (IPP), project financier and in-house counsel with exposure to the French market, these changes create immediate compliance, contractual and grid-risk obligations that demand attention before enforcement begins. This guide sets out the statutory framework, explains the practical consequences for project-level operations and financing, and provides actionable contract drafting checklists and timelines that legal teams can implement now.

Executive Summary: What Energy Lawyers and Project Teams Must Do Now

Decree No.21, read together with the updated PPE 2026 framework, creates five categories of urgent action for anyone involved in French renewable energy projects. The decree mandates participation in balancing mechanisms for all electricity generation installations with capacity of 10 MW or above, including wind and solar, effective from 31 December 2025 onward. It adjusts the PPE trajectory for offshore wind and solar, introduces stricter energy audit obligations, and reshapes the interface between generators, RTE (the French transmission system operator) and the Commission de régulation de l’énergie (CRE). The likely practical effect will be a wave of PPA renegotiations, amended grid-connection agreements and updated financing covenants across the French renewables sector.

Five immediate action items:

  • Compliance review. Audit all operational and development-stage projects against the new 10 MW balancing-participation threshold and identify which installations require RTE qualification.
  • PPA audit. Review every power purchase agreement for change-in-law clauses, imbalance cost allocation, curtailment provisions and force majeure definitions that may need amendment.
  • Grid connection studies. Confirm that existing grid-connection agreements and technical specifications meet the updated operational requirements imposed by the decree.
  • Energy audit scheduling. Calendar the new or expanded energy audit obligations and engage qualified auditors before the compliance window closes.
  • Lender notification. Brief project finance lenders on material adverse change risk, update compliance covenants and agree on contingency funding for balancing-related costs.

Law Decree No.21 (20 February 2026): Statutory Summary and Immediate Legal Effects

Law Decree No.21 was published on 20 February 2026, amending the French Energy Code (Code de l’énergie) and supplementing the existing framework established by the Energy Transition for Green Growth Act (Loi relative à la transition énergétique pour la croissance verte, LTECV). The decree operates at the intersection of the national energy strategy (PPE), grid regulation administered by CRE, and the European Union’s internal energy market rules, including the EU Electricity Regulation, which requires member states to ensure that all generation participates in balancing where technically feasible.

In practical terms, Decree No.21 does three things simultaneously: it transposes updated PPE targets into binding obligations with compliance timelines; it codifies the mandatory participation of renewables in the national balancing mechanism; and it expands the scope and frequency of energy audit requirements for operators and large energy consumers. This convergence of obligations is what makes the decree so consequential for energy lawyers France practitioners must now advise on, it is not a single-issue regulation but a multi-layered compliance event.

Key Articles of Decree No.21

Article Summary Compliance Impact
Articles 1–3 Amend the PPE trajectory: recalibrate renewable capacity targets for 2028 and 2035, including offshore wind and ground-mounted solar. Developers must reassess pipeline feasibility against revised auction volumes and permitting assumptions.
Articles 4–7 Mandate participation in the national balancing mechanism (mFRR) for all generation installations ≥10 MW, including intermittent renewables, effective from 31 December 2025. Operators of wind and solar plants ≥10 MW must complete RTE qualification, install metering and communication systems, and assume imbalance settlement exposure.
Articles 8–10 Expand energy audit obligations: broader scope of covered entities, shorter audit cycles and enhanced reporting to the relevant préfecture. Operators and large consumers must commission audits within prescribed deadlines and file remedial action plans.
Articles 11–14 Enforcement: empower CRE to impose administrative penalties for non-compliance with balancing obligations; grant préfets authority to sanction audit failures. Financial penalties and potential suspension of feed-in tariff or complément de rémunération payments for persistent non-compliance.

Enforcement, Penalties and Administrative Remedies

The enforcement architecture of Decree No.21 operates through two parallel channels. CRE retains jurisdiction over balancing-mechanism compliance and market participation, with the power to impose administrative fines. Separately, the préfet of the relevant department can sanction failures to meet energy audit obligations, including formal notice (mise en demeure) followed by escalating penalties.

Industry observers expect the most commercially significant enforcement risk to be the potential suspension or reduction of public-support payments, including the complément de rémunération, for generators that fail to participate in the balancing mechanism within the prescribed timelines. This creates a dual exposure: direct financial penalties from CRE and indirect revenue loss from suspended subsidies. For project finance structures, this combination has the potential to trigger material adverse change clauses in loan agreements and offtake contracts alike.

PPE 2026 Adjustments: Renewables Targets France 2026, Auctions and Permitting Consequences

The Programmation pluriannuelle de l’énergie (PPE) is France’s multi-year energy planning instrument, setting capacity targets and policy priorities for electricity generation across successive five-year periods. The PPE 2026 update, formally integrated into the regulatory framework through Decree No.21, adjusts the trajectory that was set by earlier iterations (PPE 2, adopted in 2020), reflecting both the acceleration of nuclear policy and a recalibration of certain renewable deployment assumptions.

The most commercially significant change concerns the offshore wind target. The PPE 2026 framework maintains the ambition of reaching approximately 15 GW of offshore wind capacity by 2035, but it restructures the interim milestones and auction scheduling in a way that compresses delivery windows for certain zones while extending them for others. For ground-mounted solar, the updated PPE raises the 2035 capacity ambition but links deployment more tightly to grid-connection readiness, meaning that projects without confirmed RTE connection dates face a higher risk of falling outside competitive auction rounds.

Comparative Table: PPE Targets, Prior Framework vs PPE 2026

Technology Prior PPE (2020/2024 Targets) PPE 2026 Adjusted Targets Practical Effect for Developers
Offshore wind ~6.2 GW by 2028; pathway to ~15 GW by 2035 Maintained 15 GW by 2035; restructured interim milestones and auction calendar Compressed delivery timelines for designated zones; higher execution risk for late-stage pipeline projects.
Ground-mounted solar Progressive annual auction rounds; flexible grid timing Raised 2035 ambition; deployment tied to confirmed grid-connection dates Projects without RTE connection certainty may miss auction eligibility windows.
Onshore wind Incremental capacity additions with regional caps Modest adjustments; stronger local acceptance and environmental conditions Permitting timelines may lengthen in contested regions; environmental impact assessments under closer scrutiny.

For energy lawyers France developers engage, the PPE 2026 changes require an immediate review of project pipelines against the revised auction calendar. Projects that assumed permitting and grid-connection timelines based on the prior PPE risk falling out of alignment with the restructured competitive rounds. Early indications suggest that the Ministry will publish updated auction specifications in the second half of 2026, and developers should engage with CRE and RTE now to secure their positions in the queue.

Operational Obligations from 2026: Balancing Mechanism Participation and Grid Rules

The most operationally disruptive element of the 2026 framework is the requirement for all electricity generation installations with a capacity of 10 MW or above to participate in France’s national balancing mechanism. This obligation, which took effect from 31 December 2025 under the regulatory timeline and is now codified through Decree No.21, applies to intermittent renewable generators, wind and solar, alongside conventional thermal and hydro assets. The requirement aligns France with the EU Electricity Regulation’s principle that all generation should contribute to system balancing where technically feasible.

Participation means that qualifying generators must be capable of responding to manual Frequency Restoration Reserve (mFRR) activation signals from RTE. In practice, this requires installation of compliant metering and real-time communication equipment, completion of RTE’s qualification process, and ongoing exposure to imbalance settlement prices. For solar and wind installations, which cannot fully control output, the obligation introduces a layer of commercial risk that was previously either absorbed by aggregators or exempted entirely.

Participation Thresholds and Timelines

Obligation Threshold Effective Date Responsible Party
Mandatory mFRR balancing participation ≥10 MW installed capacity per installation 31 December 2025 (codified by Decree No.21, 20 Feb 2026) Generator / Balance Responsible Party (BRP)
RTE technical qualification All installations subject to balancing obligation Prior to first balancing activation Generator (with RTE coordination)
Metering and communication system upgrade Compliant real-time telemetry required Concurrent with qualification Generator / asset owner
Imbalance settlement exposure Financial settlement at imbalance prices Ongoing from first participation period BRP (generator or contracted aggregator)

Market Consequences and Settlement Exposure

The financial implications of balancing mechanism participation 10 MW and above are substantial. Imbalance prices in France can be highly volatile, particularly during periods of low renewable output or unexpected demand surges. A wind farm that fails to deliver on a balancing activation signal faces settlement at the imbalance price, which may significantly exceed the contract price under the PPA or the complément de rémunération tariff.

Industry observers expect that many developers will seek to manage this exposure through aggregation arrangements, where a third-party aggregator assumes the Balance Responsible Party role and pools the balancing obligation across multiple installations. However, aggregation does not eliminate the underlying obligation, it transfers it contractually, and the generator remains ultimately responsible if the aggregator defaults. The contractual architecture between generators, aggregators and offtakers therefore becomes critical, and PPA risk allocation France structures must reflect this new reality.

Energy Audits and Corporate Compliance Obligations

Decree No.21 expands the scope and frequency of energy audit obligations 2026 operators and large energy consumers must meet. Building on the framework established by the EU Energy Efficiency Directive and its French transposition, the decree broadens the definition of covered entities, shortens audit cycles, and introduces enhanced reporting requirements to the relevant préfecture.

The immediate compliance checklist for affected entities includes:

  • Scope determination. Confirm whether the entity falls within the expanded coverage criteria based on energy consumption thresholds, employee count or turnover.
  • Audit commissioning. Engage a qualified auditor (auditeur énergétique) certified under the applicable COFRAC accreditation framework and schedule the audit within the compliance window.
  • Documentation. Prepare building-level and process-level energy consumption data, prior audit reports (if any), and evidence of implemented efficiency measures.
  • Remedial action plan. Following the audit, file a plan with the préfecture detailing proposed energy efficiency improvements, investment timelines and projected savings.
  • Ongoing reporting. Comply with any periodic reporting requirements mandated by the decree, including progress updates on remedial plan implementation.

Failure to comply with energy audit obligations can result in administrative sanctions issued by the préfet, beginning with formal notice and escalating to financial penalties. For project companies operating multiple installations, the audit obligation attaches to each qualifying site, meaning that compliance must be managed on a facility-by-facility basis.

Contract and PPA Risk Allocation: What Energy Lawyers France Practitioners Must Change Now

The convergence of new balancing obligations, revised PPE targets and expanded audit requirements means that virtually every standard-form PPA, grid-connection agreement and project finance facility agreement in France requires review. The risk allocation that was appropriate under the prior regulatory framework no longer reflects the obligations that generators and their counterparties now face.

The core drafting issues fall into four categories: allocation of imbalance and balancing costs; change-in-law provisions; operational performance warranties; and termination rights triggered by regulatory non-compliance. Each must be addressed in the context of the specific project structure, whether the generator sells under a complément de rémunération scheme, a corporate PPA, or a merchant arrangement.

Negotiation dynamics will vary depending on bargaining position. Developers will seek to pass through balancing costs to offtakers or to cap their exposure through price adjustment mechanisms. Offtakers will resist open-ended cost pass-throughs and demand performance guarantees. Lenders will require comfort that regulatory non-compliance cannot trigger subsidy suspension and thereby impair debt service coverage.

Sample Clauses

The following clause templates illustrate the key drafting responses to the 2026 changes. They should be adapted to each transaction’s specific commercial and regulatory context.

  • Balancing obligation allocation clause. “The Seller shall be responsible for complying with all balancing mechanism obligations applicable to the Facility under the Code de l’énergie as amended by Decree No.21 of 20 February 2026. All imbalance settlement costs incurred by the Seller in connection with such obligations shall be [borne by the Seller / shared between the parties in proportion to [X]% (Seller) and [Y]% (Buyer) / passed through to the Buyer as an adjustment to the Contract Price].”
  • Change-in-law clause. “If, after the date of this Agreement, any Change in Law (including Decree No.21 and any subsequent amendments to the PPE or CRE regulations) materially increases the Seller’s cost of performing its obligations hereunder, the parties shall negotiate in good faith an equitable adjustment to the Contract Price. If agreement is not reached within [60] days, either party may refer the matter to [expert determination / arbitration].”
  • Operational performance warranty. “The Seller warrants that the Facility is, and shall at all times remain, technically qualified for participation in the national balancing mechanism as required by applicable law, including installation and maintenance of compliant metering and communication systems and completion of the RTE qualification process.”
  • Regulatory non-compliance termination right. “If the Seller fails to maintain compliance with mandatory balancing-mechanism participation requirements for a continuous period exceeding [90] days, and such failure results in the suspension or reduction of any public-support payments applicable to the Facility, the Buyer shall have the right to terminate this Agreement upon [30] days’ written notice.”
  • Aggregator default indemnity. “Where the Seller delegates its balancing obligations to a third-party aggregator, the Seller shall indemnify the Buyer against all losses arising from the aggregator’s failure to perform such obligations, including any imbalance settlement costs, CRE penalties or subsidy suspensions attributable to such failure.”
  • Grid connection compliance warranty. “The Seller represents and warrants that the grid-connection agreement for the Facility complies with the technical specifications required under the Code de l’énergie as amended, and that the Facility is capable of receiving and responding to balancing activation signals from RTE.”

Grid Connection, Permitting and Financing Compliance Checklist

Beyond PPA amendments, the 2026 regulatory framework requires a parallel review of grid connection compliance, permitting conditions and financing documentation. The following consolidated checklist is designed for cross-functional legal and project teams:

  • Grid-connection agreement review. Confirm that the technical annexes to the convention de raccordement with RTE or Enedis reflect the new balancing-participation requirements, including metering specifications and communication protocols.
  • Permitting condition audit. Review all autorisation environnementale and permis de construire conditions to identify any provisions that may interact with the expanded audit obligations or revised PPE targets.
  • Bankable compliance certificate. Prepare a compliance certificate template that project companies can issue to lenders, confirming adherence to Decree No.21 requirements on a periodic basis.
  • Financing covenant update. Amend material adverse change, compliance and information-undertaking covenants in facility agreements to reflect the new regulatory framework.
  • Insurance review. Confirm that project insurance policies cover imbalance settlement exposure, CRE penalty risk and potential subsidy suspension losses.
Entity Obligation Immediate Action (Next 90 Days)
Developer (wind/solar) Mandatory balancing participation ≥10 MW; energy audits; updated grid-connection conditions Review plant MW aggregation; start RTE qualification; schedule audits; amend PPAs
Offtaker PPA operational risk allocation; performance guarantees Assess exposure to imbalance costs; seek indemnities and price adjustment clauses
Lender / Funder Compliance covenants; material adverse change risk; enforcement triggers Amend financing covenants; require compliance certificates and contingency funds

Timeline of Key Dates and Obligations

The following timeline consolidates the critical dates from Decree No.21 and the PPE 2026 framework that project teams must track:

Date / Period Event or Obligation Action Required
31 December 2025 Mandatory balancing mechanism participation takes effect for all generation ≥10 MW Complete RTE qualification; install compliant metering; designate BRP
20 February 2026 Decree No.21 published, codifying balancing obligations and PPE 2026 adjustments Legal review of all project documentation against new statutory text
H2 2026 (expected) Ministry publication of updated auction specifications reflecting PPE 2026 targets Pipeline assessment; pre-qualification filings for upcoming auction rounds
Ongoing from 2026 Expanded energy audit obligations: shorter cycles, broader entity coverage Commission qualified auditors; file remedial action plans with préfecture
21 December 2025 European Commission approval of French capacity mechanism reform under EU State aid rules Monitor reformed capacity mechanism terms; assess impact on capacity obligation certificates
2035 PPE target horizon: approximately 15 GW offshore wind Long-term pipeline planning; secure grid-connection dates aligned with auction schedule

Practical Next Steps

The 2026 regulatory framework for energy lawyers France-wide represents both a compliance challenge and a strategic opportunity. Developers, offtakers and lenders who act early, reviewing project documentation, amending PPAs and securing RTE qualification ahead of enforcement action, will be best positioned to manage the transition. Those who delay risk financial penalties, subsidy suspension and strained lender relationships. The window for proactive compliance is narrow: with balancing obligations already in effect and audit deadlines approaching, the time to engage specialist French energy counsel is now.

Need Legal Advice?

This article was produced by Global Law Experts. For specialist advice on this topic, contact Cendrine Delivré at Franklin, a member of the Global Law Experts network.

Sources

  1. Legifrance, Law Decree No.21 (Decree text)
  2. Ministry of Ecological Transition, PPE 2026 Draft
  3. RTE, Annual Electricity Review 2025
  4. CRE, Commission de régulation de l’énergie
  5. European Commission, Capacity Mechanism State Aid Approval
  6. Pexapark, France Mandates Renewables Participation in Balancing Mechanism
  7. Opoura, Renewables in France Required to Join mFRR from 2026
  8. Ministry of Economy, Strategic Environmental Assessment of the PPE

FAQs

What does France's 2026 Energy Decree (No.21) change for renewables and nuclear targets?
Decree No.21, published on 20 February 2026, recalibrates the PPE targets for offshore wind, solar and onshore wind, mandates balancing mechanism participation for all generation installations of 10 MW or above (including intermittent renewables), and expands energy audit obligations. It also strengthens CRE’s enforcement powers, including the ability to suspend public-support payments for non-compliant generators.
The PPE 2026 framework maintains the ambition of approximately 15 GW of offshore wind by 2035 but restructures interim milestones and auction scheduling. For ground-mounted solar, deployment is now more tightly linked to confirmed grid-connection dates, meaning projects without RTE connection certainty may fall outside competitive auction rounds.
All electricity generation installations with capacity of 10 MW or above must participate in the national balancing mechanism (mFRR) from 31 December 2025, as codified by Decree No.21. Additionally, expanded energy audit obligations apply to a broader range of entities, with shorter audit cycles and enhanced reporting requirements to the relevant préfecture.
Priority areas include: imbalance and balancing cost allocation clauses, change-in-law provisions referencing Decree No.21 specifically, operational performance warranties covering RTE qualification and metering compliance, termination rights triggered by subsidy suspension, and aggregator default indemnities. Sample clause templates are provided in the contract drafting section above.
CRE can impose administrative fines for failure to participate in the balancing mechanism. The préfet can sanction energy audit failures through formal notice and escalating financial penalties. The most commercially significant risk is the potential suspension or reduction of complément de rémunération payments, which can impair project revenue and trigger default provisions in financing arrangements.
Aggregation can transfer the operational responsibility for balancing participation to a third-party aggregator, but it does not eliminate the underlying obligation. The generator remains ultimately responsible if the aggregator defaults. Splitting installations into sub-10 MW units to fall below the threshold is unlikely to be effective where the installations share a single grid-connection point or are treated as a single facility under CRE’s assessment criteria.
Lenders should update material adverse change definitions to capture regulatory non-compliance risk under Decree No.21, require periodic compliance certificates from borrowers, add information undertakings covering balancing-mechanism qualification status and energy audit completion, and consider requiring contingency reserves to cover potential imbalance settlement costs or CRE penalties.

Find the right Advisory Expert for your business

The premier guide to leading advisory professionals throughout the world

Specialism
Country
Practice Area
ADVISORS RECOGNIZED
0
EVALUATIONS OF ADVISORS BY THEIR PEERS
0 m+
PRACTICE AREAS
0
COUNTRIES AROUND THE WORLD
0
Join
who are already getting the benefits
0

Sign up for the latest advisor briefings and news within Global Advisory Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.

Naturally you can unsubscribe at any time.

Newsletter Sign Up
About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Global Law Experts App

Now Available on the App & Google Play Stores.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Contact Us

Stay Informed

Join Mailing List
About Us

Global Advisory Experts is dedicated to providing exceptional advisory services to clients around the world. With a vast network of highly skilled and experienced advisors, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Global Law Experts App

Now Available on the App & Google Play Stores.

Contact Us

Stay Informed

Join Mailing List

GAE

Lawyer Profile Page - Lead Capture
GLE-Logo-White
Lawyer Profile Page - Lead Capture

Energy Lawyers France 2026: Decree No.21, PPE Targets and Project Compliance

Send welcome message

Custom Message